A leading Australian construction materials manufacturer was spending $70-130M in capital projects year on year, but not getting value for the capital deployed
Key challenges included:
The business engaged a team led by Evert Westerhof (note this was prior to Evert joining Cinc) to deliver a plan to reset the capital deployment framework ensuring that Capex was deployed on projects with highest ROI, priority assets to mitigate business risk and that project approvals and delivery was executed diligently.
The team based stay-in-business Capex on an asset criticality review, complementing this with a prioritisation of growth capex projects into a 5-year investment plan. Project approvals and delivery was addressed by rolling out a capital governance framework.
1. Asset criticality review
2. 5-year capital investment plan
3. Governance Structure
Team members involved: Evert Westerhof
This engagement was delivered prior to the team member joining Cinc. The experience and results described reflects work led by the team member(s) identified above, noting they were supported by a non-Cinc delivery team and the credential should be viewed in that context.
Annual Capex investment reduction vs. historical year-on-year spend
Annual Capex budget overspend eliminated (~$13M annually)
Due to prioritised capital investment, guided by a business-wide asset criticality review across 28 manufacturing sites
Doubled the return on investment for capital deployed across the business

Facing something similar? A senior specialist will come back to you with a view on where the value is.